Performing Arts Center — Progress Report
Phase One – Schedule:
- April 2009 - Completed Construction Drawings
- May 2009 - Break Ground on Site
- May 2009 - Begin Construction
- August 2010 - Complete Structure
- August/September 2010 - Certificate of Occupancy
Parking Lot Closures:
Effective May 9, 2009 parking lots H-1, H-2, H-3, and H-4 will be closed for the construction. Parking lots H-1 and H-2 are scheduled to reopen on June 19, 2009. Lot H-3 will remain closed until August 23, 2010. Lot H-4 is scheduled to reopen partially on June 19, 2009, (north of fence) and the remainder of the lot (south of fence) is scheduled to open August 23, 2010.